In cost accounting, prime cost is: MCQ with Answer and Explanation

In cost accounting, prime cost is:
A. Direct material + Direct labour + Direct expenses
B. Administration overheads
C. All manufacturing costs
D. Direct material + Direct labour + Factory overheads
Answer: Option A
Solution (By JKSSB Mock Tests)
Prime cost is the sum of all direct costs: direct material, direct labour, and direct expenses.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Accountancy and Book Keeping Questions

Question #1
The 'Fraud' in an audit context refers to:
A. Intentional act by one or more individuals among management, those charged with governance, employees, or third parties involving deception to obtain an unjust or illegal advantage
B. Unintentional misstatement
C. Any error
D. Negligence

Correct Answer: Option A


Explanation:
Fraud is intentional; error is unintentional.

Question #2
The 'Deduction under Section 80C' is available up to maximum of:
A. ₹1,50,000
B. ₹2,00,000
C. ₹1,00,000
D. ₹50,000

Correct Answer: Option A


Explanation:
Under Section 80C, maximum deduction is ₹1,50,000.

Question #3
In the context of taxation, the term 'PAN' stands for:
A. Public Account Number
B. Permanent Account Number
C. Personal Account Number
D. Primary Account Number

Correct Answer: Option B


Explanation:
PAN stands for Permanent Account Number, a unique 10-character alphanumeric identifier issued by the Income Tax Department of India.