Under the 'Public Financial Management System' (PFMS), the 'Just-in-Time' fund release mechanism ensures: MCQ with Answer and Explanation

Under the 'Public Financial Management System' (PFMS), the 'Just-in-Time' fund release mechanism ensures:
A. Advance payment to all
B. Release of funds only when needed, reducing idle funds
C. Manual processing
D. Delayed payments
Answer: Option B
Solution (By JKSSB Mock Tests)
Just-in-Time in PFMS releases funds just in time for expenditure, avoiding float and idle balances.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Accountancy and Book Keeping Questions

Question #1
The 'Trial Balance' is a:
A. Memorandum book
B. Subsidiary book
C. Statement
D. Principal book

Correct Answer: Option C


Explanation:
It is a statement, not a book of accounts.

Question #2
S1: In the absence of a partnership deed, interest on partner's loan is allowed at 6% per annum. S2: In the absence of a partnership deed, interest on partner's capital is not allowed. Which statement(s) is/are correct?
A. S2 only
B. Both S1 and S2
C. Neither S1 nor S2
D. S1 only

Correct Answer: Option B


Explanation:
The Partnership Act 1932 mandates that if the deed is silent, interest on a partner's loan is allowed at 6% p.a., but no interest on capital is allowed. Both statements are correct.

Question #3
A 'Cost Centre' is:
A. A method of pricing
B. A sales territory
C. A location, person, or item of equipment for which costs are accumulated
D. A unit of product

Correct Answer: Option C


Explanation:
Cost centre is a segment of the organization where costs are collected, e.g., department, machine.