11 men can complete a work in 27 days. If 15 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

11 men can complete a work in 27 days. If 15 men work at the same rate, in how many days will the work be completed?
A. 23.8
B. 25.8
C. 19.8
D. 21.8
Answer: Option C
Solution (By JKSSB Mock Tests)
Total work = 11 × 27 = 297 man-days. Required days = 297/15 = 19.8 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 19 days and B can complete the same work in 24 days. If they work together, in how many days will the work be completed?
A. 14.6
B. 16.6
C. 12.6
D. 10.6

Correct Answer: Option D


Explanation:
Combined rate = 1/19 + 1/24. Time = 1 ÷ combined rate = 10.6 days.

This question belongs to: Maths Time and Work
Question #2
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A. 8 days
B. 10 days
C. 12 days
D. 6 days

Correct Answer: Option B


Explanation:
Total work = LCM(20, 12) = 60 units. Efficiency of A = 3, B = 5. In 4 days, A alone completes = 4 * 3 = 12 units. Remaining work = 60 - 12 = 48 units. Combined efficiency of A and B = 3 + 5 = 8. Time taken together for remaining work = 48 / 8 = 6 days. Total duration of work = 4 + 6 = 10 days.

This question belongs to: Maths Time and Work
Question #3
23 men can complete a work in 30 days. If 28 men work at the same rate, the work will be completed in:
A. 29.64
B. 34.64
C. 39.64
D. 24.64

Correct Answer: Option D


Explanation:
Total work = 690 man-days. Time = 690/28 = 24.64 days.

This question belongs to: Maths Time and Work