A can complete a work in 23 days and B in 21 days. If both work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 23 days and B in 21 days. If both work together, in how many days will the work be completed?
A. 13.48
B. 15.98
C. 18.48
D. 10.98
Answer: Option D
Solution (By JKSSB Mock Tests)
Combined rate = 1/23 + 1/21. Time = 10.98 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is twice as fast as B and B is twice as fast as C. If they together can complete a work in 4 days, in how many days can C alone complete it?
A. 16 days
B. 28 days
C. 24 days
D. 32 days

Correct Answer: Option B


Explanation:
Let efficiency of C = 1, then B = 2 and A = 4. Combined efficiency = 1 + 2 + 4 = 7 units/day. Total work = 4 * 7 = 28 units. Time taken by C alone = 28 / 1 = 28 days.

This question belongs to: Maths Time and Work
Question #2
If 8 men and 12 boys can finish a piece of work in 10 days, while 6 men and 8 boys can finish it in 14 days, find the time taken by 1 man alone to complete the work.
A. 120 days
B. 140 days
C. 160 days
D. 100 days

Correct Answer: Option B


Explanation:
Total work = 10 * (8M + 12B) = 14 * (6M + 8B) => 80M + 120B = 84M + 112B => 4M = 8B => 1M = 2B. Total work = 10 * (8M + 6M) = 140M. Thus, 1 man alone will take 140 days.

This question belongs to: Maths Time and Work
Question #3
21 men can complete a work in 18 days. If 26 men work at the same rate, the work will be completed in:
A. 24.54
B. 19.54
C. 14.54
D. 29.54

Correct Answer: Option C


Explanation:
Total work = 378 man-days. Time = 378/26 = 14.54 days.