A can complete a work in 12 days and B in 25 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 12 days and B in 25 days. If they work together, the work will be completed in:
A. 23.11
B. 8.11
C. 13.11
D. 18.11
Answer: Option B
Solution (By JKSSB Mock Tests)
Combined rate = 1/12 + 1/25. Required time = 8.11 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
17 men can complete a work in 27 days. If 21 men work at the same rate, in how many days will the work be completed?
A. 27.86
B. 25.86
C. 23.86
D. 21.86

Correct Answer: Option D


Explanation:
Total work = 17 × 27 = 459 man-days. Required days = 459/21 = 21.86 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 8 days and B in 13 days. If they work together, the work will be completed in:
A. 4.95
B. 14.95
C. 19.95
D. 9.95

Correct Answer: Option A


Explanation:
Combined rate = 1/8 + 1/13. Required time = 4.95 days.

This question belongs to: Maths Time and Work
Question #3
18 men can complete a work in 22 days. If 22 men work at the same rate, in how many days will the work be completed?
A. 22.0
B. 18.0
C. 24.0
D. 20.0

Correct Answer: Option B


Explanation:
Total work = 18 × 22 = 396 man-days. Required days = 396/22 = 18.0 days.

This question belongs to: Maths Time and Work