A can complete a work in 24 days and B in 45 days. If both work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 24 days and B in 45 days. If both work together, in how many days will the work be completed?
A. 20.65
B. 18.15
C. 23.15
D. 15.65
Answer: Option D
Solution (By JKSSB Mock Tests)
Combined rate = 1/24 + 1/45. Time = 15.65 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 29 days. What percentage of the work will be completed in 7 days?
A. 26.64
B. 24.14
C. 29.14
D. 31.64

Correct Answer: Option B


Explanation:
Completed percentage = (7/29)×100 = 24.14%.

This question belongs to: Maths Time and Work
Question #2
21 men can complete a work in 29 days. If 29 men work at the same rate, how many days are required?
A. 26.0
B. 23.5
C. 28.5
D. 21.0

Correct Answer: Option D


Explanation:
Total work = 609 man-days. Days = 21.0.

This question belongs to: Maths Time and Work
Question #3
A, B and C can complete a work in 10, 12 and 15 days respectively. They start working together. Find the number of days required to complete the work.
A. 5 days
B. 4 days
C. 6 days
D. 3 days

Correct Answer: Option B


Explanation:
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Combined efficiency = 6 + 5 + 4 = 15 units/day. Time taken = 60 / 15 = 4 days.

This question belongs to: Maths Time and Work