A can complete a work in 29 days. What percentage of the work will be completed in 7 days?
A. 31.64
B. 24.14
C. 26.64
D. 29.14
Answer: Option B
Solution (By JKSSB Mock Tests)
Completed percentage = (7/29)×100 = 24.14%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
12 men can complete a piece of work in 12 days. If 6 men leave after 6 days, how many more days will it take to complete the remaining work?
A. 10 days
B. 6 days
C. 12 days
D. 8 days

Correct Answer: Option C


Explanation:
Total work = 12 * 12 = 144 man-days. In 6 days, 12 men complete = 12 * 6 = 72 man-days. Remaining work = 144 - 72 = 72 man-days. Remaining men = 12 - 6 = 6 men. Time taken by 6 men to complete remaining work = 72 / 6 = 12 days.

This question belongs to: Maths Time and Work
Question #2
A can do a work in 12 days and B in 22 days. They work together for 5 days. What percentage of work remains?
A. 50.61
B. 40.61
C. 45.61
D. 35.61

Correct Answer: Option D


Explanation:
Remaining work = (1 - 5*(1/12+1/22)) ×100 = 35.61%.

This question belongs to: Maths Time and Work
Question #3
A and B work together. A alone can complete the work in 18 days and B alone in 22 days. What percentage of the total daily work is contributed by A?
A. 55.0
B. 57.5
C. 62.5
D. 60.0

Correct Answer: Option A


Explanation:
A share = (1/18) / (1/18+1/22) ×100 = 55.0%.