12 men can complete a piece of work in 12 days. If 6 men leave after 6 days, how many more days will it take to complete the remaining work? MCQ with Answer and Explanation

12 men can complete a piece of work in 12 days. If 6 men leave after 6 days, how many more days will it take to complete the remaining work?
A. 8 days
B. 10 days
C. 12 days
D. 6 days
Answer: Option C
Solution (By JKSSB Mock Tests)
Total work = 12 * 12 = 144 man-days. In 6 days, 12 men complete = 12 * 6 = 72 man-days. Remaining work = 144 - 72 = 72 man-days. Remaining men = 12 - 6 = 6 men. Time taken by 6 men to complete remaining work = 72 / 6 = 12 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B work together. A alone can complete the work in 30 days and B alone in 30 days. What percentage of the total daily work is contributed by A?
A. 55.0
B. 57.5
C. 52.5
D. 50.0

Correct Answer: Option D


Explanation:
A share = (1/30) / (1/30+1/30) ×100 = 50.0%.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 11 days and B in 30 days. If they work together, the work will be completed in:
A. 13.05
B. 23.05
C. 18.05
D. 8.05

Correct Answer: Option D


Explanation:
Combined rate = 1/11 + 1/30. Required time = 8.05 days.

This question belongs to: Maths Time and Work
Question #3
A can do a piece of work in 10 days and B can do the same work in 15 days. If they work together, in how many days will the work be completed?
A. 8 days
B. 9 days
C. 6 days
D. 5 days

Correct Answer: Option C


Explanation:
A's 1-day work = 1/10, B's 1-day work = 1/15. Combined 1-day work = 1/10 + 1/15 = 5/30 = 1/6. Therefore, they will complete the work together in 6 days.