12 men can complete a work in 8 days. How many days will 16 men take to complete the same work? MCQ with Answer and Explanation

12 men can complete a work in 8 days. How many days will 16 men take to complete the same work?
A. 5 days
B. 7 days
C. 4 days
D. 6 days
Answer: Option D
Solution (By JKSSB Mock Tests)
Using the formula M1 * D1 = M2 * D2: 12 * 8 = 16 * D2. 96 = 16 * D2. D2 = 96 / 16 = 6 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
33 men can complete a work in 26 days. If 41 men work at the same rate, how many days are required?
A. 25.93
B. 23.43
C. 20.93
D. 28.43

Correct Answer: Option C


Explanation:
Total work = 858 man-days. Days = 20.93.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 25 days and B in 25 days. If both work together, in how many days will the work be completed?
A. 15.0
B. 12.5
C. 20.0
D. 17.5

Correct Answer: Option B


Explanation:
Combined rate = 1/25 + 1/25. Time = 12.5 days.

This question belongs to: Maths Time and Work
Question #3
A can do a piece of work in 24 days, B in 32 days, and C in 64 days. They start together but A leaves after 6 days and B leaves 6 days before the completion of the work. Find the total number of days taken to complete the work.
A. 24 days
B. 18 days
C. 16 days
D. 20 days

Correct Answer: Option D


Explanation:
Total work = LCM(24, 32, 64) = 192 units. Efficiency of A = 8, B = 6, C = 3. Let total days be x. A works for 6 days. B works for (x - 6) days. C works for x days. Total work = 6*8 + (x - 6)*6 + x*3 = 192 => 48 + 6x - 36 + 3x = 192 => 9x + 12 = 192 => 9x = 180 => x = 20 days.

This question belongs to: Maths Time and Work