33 men can complete a work in 26 days. If 41 men work at the same rate, how many days are required? MCQ with Answer and Explanation

33 men can complete a work in 26 days. If 41 men work at the same rate, how many days are required?
A. 23.43
B. 28.43
C. 20.93
D. 25.93
Answer: Option C
Solution (By JKSSB Mock Tests)
Total work = 858 man-days. Days = 20.93.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
10 men can complete a work in 14 days. If 14 men work at the same rate, in how many days will the work be completed?
A. 10.0
B. 12.0
C. 14.0
D. 16.0

Correct Answer: Option A


Explanation:
Total work = 10 × 14 = 140 man-days. Required days = 140/14 = 10.0 days.

This question belongs to: Maths Time and Work
Question #2
A and B can complete a piece of work in 12 and 18 days respectively. They begin the work together, but A leaves 4 days before the completion of the work. For how many days did A and B work together?
A. 5 days
B. 6 days
C. 4.4 days
D. 5.6 days

Correct Answer: Option D


Explanation:
Total work = LCM(12, 18) = 36 units. Efficiency of A = 3, B = 2. Let total days be x. B works for x days, A works for (x - 4) days. 3(x - 4) + 2x = 36 => 3x - 12 + 2x = 36 => 5x = 48 => x = 9.6 days. A and B worked together for x - 4 = 9.6 - 4 = 5.6 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 16 days and B in 29 days. If they work together, the work will be completed in:
A. 10.31
B. 20.31
C. 25.31
D. 15.31

Correct Answer: Option A


Explanation:
Combined rate = 1/16 + 1/29. Required time = 10.31 days.

This question belongs to: Maths Time and Work