A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier than the scheduled time. How many days would it have been delayed if 5 more men were not employed?
Explanation:
Scheduled time = 38 days. Work finished 1 day earlier, so it took 37 days. For the first 25 days, 30 men worked. For the remaining 37 - 25 = 12 days, 35 men worked. Remaining work = 35 * 12 = 420 man-days. If 5 extra men were not joined, 30 men would take 420 / 30 = 14 days to complete this remaining work. Total days taken without extra men = 25 + 14 = 39 days. Delay = 39 - 38 = 1 day.