19 men can complete a work in 26 days. If 24 men work at the same rate, the work will be completed in: MCQ with Answer and Explanation

19 men can complete a work in 26 days. If 24 men work at the same rate, the work will be completed in:
A. 35.58
B. 25.58
C. 20.58
D. 30.58
Answer: Option C
Solution (By JKSSB Mock Tests)
Total work = 494 man-days. Time = 494/24 = 20.58 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
14 men can complete a work in 26 days. If 19 men work at the same rate, the work will be completed in:
A. 34.16
B. 19.16
C. 24.16
D. 29.16

Correct Answer: Option B


Explanation:
Total work = 364 man-days. Time = 364/19 = 19.16 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 21 days and B in 38 days. If both work together, in how many days will the work be completed?
A. 21.03
B. 16.03
C. 18.53
D. 13.53

Correct Answer: Option D


Explanation:
Combined rate = 1/21 + 1/38. Time = 13.53 days.

This question belongs to: Maths Time and Work
Question #3
18 men can complete a work in 28 days. If 22 men work at the same rate, in how many days will the work be completed?
A. 24.91
B. 26.91
C. 28.91
D. 22.91

Correct Answer: Option D


Explanation:
Total work = 18 × 28 = 504 man-days. Required days = 504/22 = 22.91 days.

This question belongs to: Maths Time and Work