14 men can complete a work in 26 days. If 19 men work at the same rate, the work will be completed in: MCQ with Answer and Explanation

14 men can complete a work in 26 days. If 19 men work at the same rate, the work will be completed in:
A. 19.16
B. 29.16
C. 24.16
D. 34.16
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = 364 man-days. Time = 364/19 = 19.16 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 15 days and B can complete the same work in 20 days. If they work together, in how many days will the work be completed?
A. 12.57
B. 14.57
C. 10.57
D. 8.57

Correct Answer: Option D


Explanation:
Combined rate = 1/15 + 1/20. Time = 1 ÷ combined rate = 8.57 days.

This question belongs to: Maths Time and Work
Question #2
If 10 men or 20 women can do a piece of work in 13 days, in how many days will 24 men and 17 women complete the same work?
A. 4 days
B. 6 days
C. 5 days
D. 7 days

Correct Answer: Option A


Explanation:
10 Men = 20 Women => 1 Man = 2 Women. 24 men + 17 women = 24 * 2 + 17 = 48 + 17 = 65 women. Since 20 women do the work in 13 days, 65 women will do it in (20 * 13) / 65 = 260 / 65 = 4 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 19 days and B can complete the same work in 24 days. If they work together, in how many days will the work be completed?
A. 12.6
B. 16.6
C. 10.6
D. 14.6

Correct Answer: Option C


Explanation:
Combined rate = 1/19 + 1/24. Time = 1 ÷ combined rate = 10.6 days.

This question belongs to: Maths Time and Work