A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. In how many days will A, B, and C finish it working together? MCQ with Answer and Explanation

A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. In how many days will A, B, and C finish it working together?
A. 8 days
B. 12 days
C. 5 days
D. 10 days
Answer: Option D
Solution (By JKSSB Mock Tests)
2(A + B + C)'s 1-day work = 1/12 + 1/15 + 1/20 = 12/60 = 1/5. Therefore, (A + B + C)'s 1-day work = 1/10. Working together, they finish in 10 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is twice as fast as B. If A and B together can complete a piece of work in 8 days, in how many days can A alone complete it?
A. 16 days
B. 10 days
C. 24 days
D. 12 days

Correct Answer: Option D


Explanation:
Let efficiency of B = 1, then efficiency of A = 2. Combined efficiency = 3 units/day. Total work = 8 * 3 = 24 units. Time taken by A alone = 24 / 2 = 12 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 19 days and B in 19 days. If they work together, the work will be completed in:
A. 14.5
B. 19.5
C. 24.5
D. 9.5

Correct Answer: Option D


Explanation:
Combined rate = 1/19 + 1/19. Required time = 9.5 days.

This question belongs to: Maths Time and Work
Question #3
A and B can do a work in 12 days, B and C in 15 days, and C and A in 20 days. How many days will A alone take to finish the work?
A. 30 days
B. 40 days
C. 60 days
D. 20 days

Correct Answer: Option A


Explanation:
Total work = LCM(12, 15, 20) = 60 units. Efficiency of (A+B) = 5, (B+C) = 4, (C+A) = 3. Summing efficiencies gives 2*(A+B+C) = 12 => Efficiency of (A+B+C) = 6 units/day. Efficiency of A = (A+B+C) - (B+C) = 6 - 4 = 2 units/day. Time taken by A alone = 60 / 2 = 30 days.

This question belongs to: Maths Time and Work