A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. In how many days will A, B, and C finish it working together? MCQ with Answer and Explanation

A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. In how many days will A, B, and C finish it working together?
A. 5 days
B. 8 days
C. 10 days
D. 12 days
Answer: Option C
Solution (By JKSSB Mock Tests)
2(A + B + C)'s 1-day work = 1/12 + 1/15 + 1/20 = 12/60 = 1/5. Therefore, (A + B + C)'s 1-day work = 1/10. Working together, they finish in 10 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 10 days and B in 20 days. After working together for 5 days, what percentage of work remains?
A. 27.5
B. 25.0
C. 32.5
D. 30.0

Correct Answer: Option B


Explanation:
Remaining work = (1 - 5*(1/10+1/20))×100 = 25.0%.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 19 days and B can complete the same work in 19 days. If they work together, in how many days will the work be completed?
A. 9.5
B. 11.5
C. 15.5
D. 13.5

Correct Answer: Option A


Explanation:
Combined rate = 1/19 + 1/19. Time = 1 ÷ combined rate = 9.5 days.

This question belongs to: Maths Time and Work
Question #3
17 men can complete a work in 14 days. If 22 men work at the same rate, the work will be completed in:
A. 10.82
B. 20.82
C. 15.82
D. 25.82

Correct Answer: Option A


Explanation:
Total work = 238 man-days. Time = 238/22 = 10.82 days.

This question belongs to: Maths Time and Work