17 men can complete a work in 14 days. If 22 men work at the same rate, the work will be completed in: MCQ with Answer and Explanation

17 men can complete a work in 14 days. If 22 men work at the same rate, the work will be completed in:
A. 25.82
B. 20.82
C. 15.82
D. 10.82
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = 238 man-days. Time = 238/22 = 10.82 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 22 days and B in 20 days. If they work together, the work will be completed in:
A. 10.48
B. 15.48
C. 25.48
D. 20.48

Correct Answer: Option A


Explanation:
Combined rate = 1/22 + 1/20. Required time = 10.48 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 16 days and B in 32 days. After working together for 5 days, what percentage of work remains?
A. 55.62
B. 60.62
C. 58.12
D. 53.12

Correct Answer: Option D


Explanation:
Remaining work = (1 - 5*(1/16+1/32))×100 = 53.12%.

This question belongs to: Maths Time and Work
Question #3
19 men can complete a work in 32 days. If 27 men work at the same rate, how many days are required?
A. 22.52
B. 25.02
C. 30.02
D. 27.52

Correct Answer: Option A


Explanation:
Total work = 608 man-days. Days = 22.52.

This question belongs to: Maths Time and Work