A can complete a work in 16 days and B in 32 days. After working together for 5 days, what percentage of work remains? MCQ with Answer and Explanation

A can complete a work in 16 days and B in 32 days. After working together for 5 days, what percentage of work remains?
A. 60.62
B. 55.62
C. 58.12
D. 53.12
Answer: Option D
Solution (By JKSSB Mock Tests)
Remaining work = (1 - 5*(1/16+1/32))×100 = 53.12%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is twice as fast as B. If B can complete a work in 12 days, in how many days can A and B together complete the work?
A. 8 days
B. 4 days
C. 3 days
D. 6 days

Correct Answer: Option B


Explanation:
B takes 12 days, so A takes 6 days. Total work = 12 units. Efficiency of A = 2, B = 1. Combined efficiency = 3 units/day. Time taken together = 12 / 3 = 4 days.

This question belongs to: Maths Time and Work
Question #2
A can do a piece of work in 40 days. He works at it for 8 days and then B finishes it in 16 days. How long will A and B together take to complete the work?
A. 25 days
B. 13(1/3) days
C. 20 days
D. 15 days

Correct Answer: Option B


Explanation:
Let total work be 40 units. Efficiency of A = 1 unit/day. In 8 days, A completes 8 units. Remaining work = 40 - 8 = 32 units. B finishes 32 units in 16 days, so B's efficiency = 32 / 16 = 2 units/day. Combined efficiency of A and B = 1 + 2 = 3 units/day. Time taken together = 40 / 3 = 13(1/3) days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 24 days and B in 29 days. If they work together, the work will be completed in:
A. 28.13
B. 18.13
C. 23.13
D. 13.13

Correct Answer: Option D


Explanation:
Combined rate = 1/24 + 1/29. Required time = 13.13 days.

This question belongs to: Maths Time and Work