A can complete a work in 16 days and B in 32 days. After working together for 5 days, what percentage of work remains? MCQ with Answer and Explanation

A can complete a work in 16 days and B in 32 days. After working together for 5 days, what percentage of work remains?
A. 58.12
B. 55.62
C. 60.62
D. 53.12
Answer: Option D
Solution (By JKSSB Mock Tests)
Remaining work = (1 - 5*(1/16+1/32))×100 = 53.12%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 15 days and B in 30 days. After working together for 5 days, what percentage of work remains?
A. 50.0
B. 55.0
C. 57.5
D. 52.5

Correct Answer: Option A


Explanation:
Remaining work = (1 - 5*(1/15+1/30))×100 = 50.0%.

This question belongs to: Maths Time and Work
Question #2
A can do a piece of work in 12 days and B can do the same work in 18 days. They work together for 4 days and then A leaves. How many days will B take to complete the remaining work?
A. 5 days
B. 6 days
C. 8 days
D. 7 days

Correct Answer: Option C


Explanation:
Total work = LCM(12, 18) = 36 units. Efficiency of A = 3, B = 2. Combined efficiency = 5. In 4 days, work completed = 4 * 5 = 20 units. Remaining work = 36 - 20 = 16 units. Time taken by B to complete the remaining work = 16 / 2 = 8 days.

This question belongs to: Maths Time and Work
Question #3
A can do a piece of work in 14 days and B in 21 days. They begin together but 3 days before the completion of the work, A leaves. The total number of days taken to complete the work is:
A. 9(1/5) days
B. 10(1/5) days
C. 8(3/5) days
D. 7(2/5) days

Correct Answer: Option B


Explanation:
Total work = LCM(14, 21) = 42 units. Efficiency of A = 3, B = 2. Let total days be x. A works for (x - 3) days and B works for x days. 3*(x - 3) + 2*x = 42 => 3x - 9 + 2x = 42 => 5x = 51 => x = 51/5 = 10(1/5) days.

This question belongs to: Maths Time and Work