A can do a work in 20 days and B in 30 days. They work together for 7 days and then both leave. Then C alone finishes the remaining work in 10 days. In how many days will C alone finish the whole work? MCQ with Answer and Explanation

A can do a work in 20 days and B in 30 days. They work together for 7 days and then both leave. Then C alone finishes the remaining work in 10 days. In how many days will C alone finish the whole work?
A. 25 days
B. 40 days
C. 30 days
D. 24 days
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. Combined efficiency = 5 units/day. In 7 days, work done = 7 * 5 = 35 units. Remaining work = 60 - 35 = 25 units. C's efficiency = 25 units / 10 days = 2.5 units/day. Days for C to complete total work = 60 / 2.5 = 24 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 14 days and B in 28 days. After working together for 5 days, what percentage of work remains?
A. 46.43
B. 48.93
C. 53.93
D. 51.43

Correct Answer: Option A


Explanation:
Remaining work = (1 - 5*(1/14+1/28))×100 = 46.43%.

This question belongs to: Maths Time and Work
Question #2
A is 50% more efficient than B. If A can complete a piece of work in 12 days, in how many days can B complete the same work?
A. 20 days
B. 15 days
C. 24 days
D. 18 days

Correct Answer: Option D


Explanation:
Let efficiency of B = 2, then efficiency of A = 3. Total work = Efficiency of A * Time of A = 3 * 12 = 36 units. Time taken by B = 36 / 2 = 18 days.

This question belongs to: Maths Time and Work
Question #3
11 men can complete a work in 27 days. If 15 men work at the same rate, in how many days will the work be completed?
A. 19.8
B. 25.8
C. 23.8
D. 21.8

Correct Answer: Option A


Explanation:
Total work = 11 × 27 = 297 man-days. Required days = 297/15 = 19.8 days.

This question belongs to: Maths Time and Work