14 men can complete a work in 12 days. If 18 men work at the same rate, in how many days will the work be completed?
A. 15.33
B. 13.33
C. 9.33
D. 11.33
Answer: Option C
Solution (By JKSSB Mock Tests)
Total work = 14 × 12 = 168 man-days. Required days = 168/18 = 9.33 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 22 days and B in 12 days. If they work together, the work will be completed in:
A. 22.76
B. 12.76
C. 7.76
D. 17.76

Correct Answer: Option C


Explanation:
Combined rate = 1/22 + 1/12. Required time = 7.76 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 21 days and B in 17 days. If they work together, the work will be completed in:
A. 24.39
B. 19.39
C. 9.39
D. 14.39

Correct Answer: Option C


Explanation:
Combined rate = 1/21 + 1/17. Required time = 9.39 days.

This question belongs to: Maths Time and Work
Question #3
12 men can complete a work in 16 days. If 16 men work at the same rate, in how many days will the work be completed?
A. 14.0
B. 12.0
C. 18.0
D. 16.0

Correct Answer: Option B


Explanation:
Total work = 12 × 16 = 192 man-days. Required days = 192/16 = 12.0 days.

This question belongs to: Maths Time and Work