15 men can complete a work in 25 days. If 19 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

15 men can complete a work in 25 days. If 19 men work at the same rate, in how many days will the work be completed?
A. 25.74
B. 21.74
C. 23.74
D. 19.74
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = 15 × 25 = 375 man-days. Required days = 375/19 = 19.74 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 11 days and B can complete the same work in 21 days. If they work together, in how many days will the work be completed?
A. 7.22
B. 9.22
C. 11.22
D. 13.22

Correct Answer: Option A


Explanation:
Combined rate = 1/11 + 1/21. Time = 1 ÷ combined rate = 7.22 days.

This question belongs to: Maths Time and Work
Question #2
A and B work together. A alone can complete the work in 30 days and B alone in 28 days. What percentage of the total daily work is contributed by A?
A. 48.28
B. 53.28
C. 55.78
D. 50.78

Correct Answer: Option A


Explanation:
A share = (1/30) / (1/30+1/28) ×100 = 48.28%.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 22 days and B in 12 days. If they work together, the work will be completed in:
A. 12.76
B. 17.76
C. 7.76
D. 22.76

Correct Answer: Option C


Explanation:
Combined rate = 1/22 + 1/12. Required time = 7.76 days.

This question belongs to: Maths Time and Work