16 men can complete a work in 20 days. If 20 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

16 men can complete a work in 20 days. If 20 men work at the same rate, in how many days will the work be completed?
A. 22.0
B. 20.0
C. 18.0
D. 16.0
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = 16 × 20 = 320 man-days. Required days = 320/20 = 16.0 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is twice as efficient as B. If they complete a work together in 14 days, how many days will A alone take to complete it?
A. 21 days
B. 35 days
C. 42 days
D. 28 days

Correct Answer: Option A


Explanation:
Let efficiency of B = 1, then efficiency of A = 2. Combined efficiency = 3. Total work = 14 * 3 = 42 units. Time taken by A alone = 42 / 2 = 21 days.

This question belongs to: Maths Time and Work
Question #2
13 men can complete a work in 23 days. If 17 men work at the same rate, in how many days will the work be completed?
A. 19.59
B. 21.59
C. 23.59
D. 17.59

Correct Answer: Option D


Explanation:
Total work = 13 × 23 = 299 man-days. Required days = 299/17 = 17.59 days.

This question belongs to: Maths Time and Work
Question #3
12 men can complete a work in 8 days. How many days will it take for 16 men to complete the same work?
A. 4 days
B. 5 days
C. 6 days
D. 7 days

Correct Answer: Option C


Explanation:
Using M1 * D1 = M2 * D2: 12 * 8 = 16 * D2. 96 = 16 * D2. D2 = 96 / 16 = 6 days.

This question belongs to: Maths Time and Work