16 men can complete a work in 26 days. If 20 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

16 men can complete a work in 26 days. If 20 men work at the same rate, in how many days will the work be completed?
A. 22.8
B. 26.8
C. 24.8
D. 20.8
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = 16 × 26 = 416 man-days. Required days = 416/20 = 20.8 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 18 days and B in 27 days. If they work together, the work will be completed in:
A. 10.8
B. 15.8
C. 25.8
D. 20.8

Correct Answer: Option A


Explanation:
Combined rate = 1/18 + 1/27. Required time = 10.8 days.

This question belongs to: Maths Time and Work
Question #2
A is twice as efficient as B and B is twice as efficient as C. If A and B together can complete a work in 4 days, then C alone can complete it in:
A. 16 days
B. 32 days
C. 24 days
D. 12 days

Correct Answer: Option C


Explanation:
Let efficiency of C = 1. Then efficiency of B = 2 and efficiency of A = 4. Combined efficiency of A and B = 4 + 2 = 6. Total work = 4 * 6 = 24 units. Time taken by C alone = 24 / 1 = 24 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 13 days and B in 42 days. If both work together, in how many days will the work be completed?
A. 9.93
B. 12.43
C. 17.43
D. 14.93

Correct Answer: Option A


Explanation:
Combined rate = 1/13 + 1/42. Time = 9.93 days.