17 men can complete a work in 21 days. If 21 men work at the same rate, in how many days will the work be completed?
A. 17.0
B. 19.0
C. 21.0
D. 23.0
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = 17 × 21 = 357 man-days. Required days = 357/21 = 17.0 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 10 days and B in 27 days. If they work together, the work will be completed in:
A. 7.3
B. 22.3
C. 17.3
D. 12.3

Correct Answer: Option A


Explanation:
Combined rate = 1/10 + 1/27. Required time = 7.3 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 26 days. What percentage of work will A complete in 6 days?
A. 38.08
B. 33.08
C. 28.08
D. 23.08

Correct Answer: Option D


Explanation:
Percentage completed = (6/26) × 100 = 23.08%.

This question belongs to: Maths Time and Work
Question #3
19 men can complete a work in 17 days. If 23 men work at the same rate, in how many days will the work be completed?
A. 14.04
B. 16.04
C. 18.04
D. 20.04

Correct Answer: Option A


Explanation:
Total work = 19 × 17 = 323 man-days. Required days = 323/23 = 14.04 days.