18 men can complete a work in 30 days. If 23 men work at the same rate, the work will be completed in: MCQ with Answer and Explanation

18 men can complete a work in 30 days. If 23 men work at the same rate, the work will be completed in:
A. 33.48
B. 23.48
C. 28.48
D. 38.48
Answer: Option B
Solution (By JKSSB Mock Tests)
Total work = 540 man-days. Time = 540/23 = 23.48 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
If 5 men can complete a work in 6 days, and 10 women can complete the same work in 5 days, in how many days can 5 men and 5 women complete the work together?
A. 3.75 days
B. 4 days
C. 4.5 days
D. 3 days

Correct Answer: Option A


Explanation:
Efficiency of 5 men = 1/6. Efficiency of 10 women = 1/5, so efficiency of 5 women = 1/10. Combined efficiency of 5 men and 5 women = 1/6 + 1/10 = (5 + 3) / 30 = 8 / 30 = 4 / 15. Time taken together = 15 / 4 = 3.75 days.

This question belongs to: Maths Time and Work
Question #2
A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave. Then C alone finishes the remaining work in 10 days. In how many days can C alone finish the full work?
A. 35 days
B. 24 days
C. 30 days
D. 25 days

Correct Answer: Option B


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. Combined efficiency = 5 units/day. In 7 days, work done = 7 * 5 = 35 units. Remaining work = 60 - 35 = 25 units. C takes 10 days to do 25 units, so efficiency of C = 25 / 10 = 2.5 units/day. Time taken by C for full work = 60 / 2.5 = 24 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 17 days and B can complete the same work in 17 days. If they work together, in how many days will the work be completed?
A. 8.5
B. 12.5
C. 10.5
D. 14.5

Correct Answer: Option A


Explanation:
Combined rate = 1/17 + 1/17. Time = 1 ÷ combined rate = 8.5 days.