A and B can complete a piece of work in 18 days and 24 days respectively. They worked together for 6 days and then A left. In how many days will B complete the remaining work? MCQ with Answer and Explanation

A and B can complete a piece of work in 18 days and 24 days respectively. They worked together for 6 days and then A left. In how many days will B complete the remaining work?
A. 12 days
B. 10 days
C. 14 days
D. 8 days
Answer: Option B
Solution (By JKSSB Mock Tests)
Total work = LCM(18, 24) = 72 units. Efficiency of A = 4, B = 3. Combined efficiency = 7. In 6 days, work done = 6 * 7 = 42 units. Remaining work = 72 - 42 = 30 units. Time taken by B to finish remaining work = 30 / 3 = 10 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 19 days and B can complete the same work in 34 days. If they work together, in how many days will the work be completed?
A. 18.19
B. 14.19
C. 16.19
D. 12.19

Correct Answer: Option D


Explanation:
Combined rate = 1/19 + 1/34. Time = 1 ÷ combined rate = 12.19 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 11 days and B in 22 days. If they work together, the work will be completed in:
A. 12.33
B. 7.33
C. 22.33
D. 17.33

Correct Answer: Option B


Explanation:
Combined rate = 1/11 + 1/22. Required time = 7.33 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a project in 20 days and B in 30 days. If they work on alternate days starting with A, in how many days will the project be completed?
A. 24 days
B. 25 days
C. 26 days
D. 22 days

Correct Answer: Option A


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In a 2-day cycle (A then B), work completed = 3 + 2 = 5 units. Number of cycles required = 60 / 5 = 12 cycles. Total time = 12 * 2 = 24 days.