A and B can complete a piece of work in 20 days and 30 days respectively. If they work on alternate days starting with B, in how many days will the work be finished? MCQ with Answer and Explanation

A and B can complete a piece of work in 20 days and 30 days respectively. If they work on alternate days starting with B, in how many days will the work be finished?
A. 26 days
B. 23 days
C. 25 days
D. 24 days
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In 2 days (B then A), work completed = 2 + 3 = 5 units. Time taken to complete 60 units = (60 / 5) * 2 = 24 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
18 men can complete a work in 22 days. If 22 men work at the same rate, in how many days will the work be completed?
A. 18.0
B. 24.0
C. 22.0
D. 20.0

Correct Answer: Option A


Explanation:
Total work = 18 × 22 = 396 man-days. Required days = 396/22 = 18.0 days.

This question belongs to: Maths Time and Work
Question #2
15 men can complete a work in 22 days. If 20 men work at the same rate, the work will be completed in:
A. 26.5
B. 16.5
C. 31.5
D. 21.5

Correct Answer: Option B


Explanation:
Total work = 330 man-days. Time = 330/20 = 16.5 days.

This question belongs to: Maths Time and Work
Question #3
A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start together but C leaves 4 days before the completion of the work. In how many days was the work completed?
A. 13 days
B. 10 days
C. 11 days
D. 12 days

Correct Answer: Option C


Explanation:
Total work = LCM(24, 30, 40) = 120 units. Efficiency of A = 5, B = 4, C = 3. Let the total number of days be x. A and B work for x days, while C works for (x - 4) days. 5x + 4x + 3(x - 4) = 120 => 12x - 12 = 120 => 12x = 132 => x = 11 days.

This question belongs to: Maths Time and Work