A and B can complete a piece of work in 20 days and 30 days respectively. If they work on alternate days starting with B, in how many days will the work be finished? MCQ with Answer and Explanation

A and B can complete a piece of work in 20 days and 30 days respectively. If they work on alternate days starting with B, in how many days will the work be finished?
A. 24 days
B. 23 days
C. 26 days
D. 25 days
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In 2 days (B then A), work completed = 2 + 3 = 5 units. Time taken to complete 60 units = (60 / 5) * 2 = 24 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is twice as efficient as B, and C is thrice as efficient as B. If they working together can finish a work in 5 days, in how many days can A alone finish it?
A. 10 days
B. 18 days
C. 15 days
D. 12 days

Correct Answer: Option C


Explanation:
Let efficiency of B = 1. Then efficiency of A = 2, and efficiency of C = 3. Combined efficiency = 1 + 2 + 3 = 6. Total work = 5 * 6 = 30 units. Time taken by A alone = 30 / 2 = 15 days.

This question belongs to: Maths Time and Work
Question #2
A can do a work in 15 days and B in 23 days. In how many days will they complete 75% of the work together?
A. 9.31
B. 11.81
C. 6.81
D. 14.31

Correct Answer: Option C


Explanation:
Combined time for full work multiplied by 0.75 = 6.81 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 15 days and B in 15 days. If they work together, the work will be completed in:
A. 7.5
B. 12.5
C. 22.5
D. 17.5

Correct Answer: Option A


Explanation:
Combined rate = 1/15 + 1/15. Required time = 7.5 days.

This question belongs to: Maths Time and Work