A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start together but C leaves 4 days before the completion of the work. In how many days was the work completed? MCQ with Answer and Explanation

A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start together but C leaves 4 days before the completion of the work. In how many days was the work completed?
A. 10 days
B. 12 days
C. 13 days
D. 11 days
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = LCM(24, 30, 40) = 120 units. Efficiency of A = 5, B = 4, C = 3. Let the total number of days be x. A and B work for x days, while C works for (x - 4) days. 5x + 4x + 3(x - 4) = 120 => 12x - 12 = 120 => 12x = 132 => x = 11 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is thrice as efficient as B. Working together, they can complete a piece of work in 18 days. In how many days can A alone complete the work?
A. 54 days
B. 36 days
C. 72 days
D. 24 days

Correct Answer: Option D


Explanation:
Let B's efficiency = 1, then A's efficiency = 3. Combined efficiency = 3 + 1 = 4. Total work = 18 * 4 = 72 units. Time taken by A alone = 72 / 3 = 24 days.

This question belongs to: Maths Time and Work
Question #2
If 12 men and 16 boys can do a piece of work in 5 days; while 13 men and 24 boys can do it in 4 days, then the ratio of the daily work done by a man to that of a boy is:
A. 3 : 1
B. 5 : 4
C. 2 : 1
D. 3 : 2

Correct Answer: Option C


Explanation:
Total work = 5 * (12M + 16B) = 4 * (13M + 24B) => 60M + 80B = 52M + 96B => 8M = 16B => M/B = 16/8 = 2/1. Thus, the ratio is 2 : 1.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 20 days and B in 30 days. They start together but A leaves after 4 days. In how many total days will the work be completed?
A. 16 days
B. 25 days
C. 20 days
D. 24 days

Correct Answer: Option D


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In 4 days, work completed = 4 * (3 + 2) = 20 units. Remaining work = 60 - 20 = 40 units. Time taken by B to finish remaining work = 40 / 2 = 20 days. Total days = 4 + 20 = 24 days.

This question belongs to: Maths Time and Work