A can complete a work in 20 days and B in 30 days. They start together but A leaves after 4 days. In how many total days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 20 days and B in 30 days. They start together but A leaves after 4 days. In how many total days will the work be completed?
A. 20 days
B. 16 days
C. 24 days
D. 25 days
Answer: Option C
Solution (By JKSSB Mock Tests)
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In 4 days, work completed = 4 * (3 + 2) = 20 units. Remaining work = 60 - 20 = 40 units. Time taken by B to finish remaining work = 40 / 2 = 20 days. Total days = 4 + 20 = 24 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is 40% more efficient than B. If B alone can complete a work in 14 days, then in how many days can A alone complete the same work?
A. 10 days
B. 8 days
C. 12 days
D. 9 days

Correct Answer: Option A


Explanation:
Let efficiency of B = 100, then efficiency of A = 140. Ratio of efficiency of A : B = 140 : 100 = 7 : 5. Total work = Efficiency of B * Time of B = 5 * 14 = 70 units. Time taken by A alone = 70 / 7 = 10 days.

This question belongs to: Maths Time and Work
Question #2
A can do a work in 14 days and B in 21 days. They begin together but 3 days before the completion of the work, A leaves. What is the total number of days taken to complete the work?
A. 10(1/5) days
B. 8(3/5) days
C. 9(1/5) days
D. 11(2/5) days

Correct Answer: Option A


Explanation:
Total work = LCM(14, 21) = 42 units. Efficiency of A = 3, B = 2. Let total days be x. A works for (x - 3) days and B works for x days. 3(x - 3) + 2x = 42 => 3x - 9 + 2x = 42 => 5x = 51 => x = 51/5 = 10(1/5) days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 17 days and B can complete the same work in 17 days. If they work together, in how many days will the work be completed?
A. 14.5
B. 8.5
C. 10.5
D. 12.5

Correct Answer: Option B


Explanation:
Combined rate = 1/17 + 1/17. Time = 1 ÷ combined rate = 8.5 days.

This question belongs to: Maths Time and Work