A can do a work in 14 days and B in 21 days. They begin together but 3 days before the completion of the work, A leaves. What is the total number of days taken to complete the work? MCQ with Answer and Explanation
A can do a work in 14 days and B in 21 days. They begin together but 3 days before the completion of the work, A leaves. What is the total number of days taken to complete the work?
A. 8(3/5) days
B. 9(1/5) days
C. 11(2/5) days
D. 10(1/5) days
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = LCM(14, 21) = 42 units. Efficiency of A = 3, B = 2. Let total days be x. A works for (x - 3) days and B works for x days. 3(x - 3) + 2x = 42 => 3x - 9 + 2x = 42 => 5x = 51 => x = 51/5 = 10(1/5) days.