A can complete a work in 25 days and B in 50 days. After working together for 5 days, what percentage of work remains? MCQ with Answer and Explanation

A can complete a work in 25 days and B in 50 days. After working together for 5 days, what percentage of work remains?
A. 77.5
B. 75.0
C. 72.5
D. 70.0
Answer: Option D
Solution (By JKSSB Mock Tests)
Remaining work = (1 - 5*(1/25+1/50))×100 = 70.0%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
17 men can complete a work in 20 days. If 25 men work at the same rate, how many days are required?
A. 16.1
B. 13.6
C. 21.1
D. 18.6

Correct Answer: Option B


Explanation:
Total work = 340 man-days. Days = 13.6.

This question belongs to: Maths Time and Work
Question #2
A is twice as fast as B and B is thrice as fast as C. If C alone can complete the work in 24 days, in how many days can they together finish the work?
A. 2.4 days
B. 4 days
C. 3 days
D. 2.6 days

Correct Answer: Option A


Explanation:
Let efficiency of C = 1. Then efficiency of B = 3 * 1 = 3. Efficiency of A = 2 * 3 = 6. Total work = Efficiency of C * Time of C = 1 * 24 = 24 units. Combined efficiency of A, B and C = 6 + 3 + 1 = 10. Time taken together = 24 / 10 = 2.4 days.

This question belongs to: Maths Time and Work
Question #3
A and B together can complete a piece of work in 12 days. They worked together for 4 days and then A left. B finished the remaining work alone in 14 more days. In how many days can A alone complete the work?
A. 28 days
B. 35 days
C. 42 days
D. 21 days

Correct Answer: Option A


Explanation:
Let combined efficiency of A and B be 1 unit/day, so total work = 12 units. In 4 days, they complete 4 units. Remaining work = 12 - 4 = 8 units. B completes 8 units in 14 days, so B's efficiency = 8 / 14 = 4/7 units/day. Efficiency of A = 1 - 4/7 = 3/7 units/day. Time taken by A alone = 12 / (3/7) = (12 * 7) / 3 = 28 days.

This question belongs to: Maths Time and Work