A and B together can complete a piece of work in 12 days. They worked together for 4 days and then A left. B finished the remaining work alone in 14 more days. In how many days can A alone complete the work? MCQ with Answer and Explanation

A and B together can complete a piece of work in 12 days. They worked together for 4 days and then A left. B finished the remaining work alone in 14 more days. In how many days can A alone complete the work?
A. 42 days
B. 28 days
C. 35 days
D. 21 days
Answer: Option B
Solution (By JKSSB Mock Tests)
Let combined efficiency of A and B be 1 unit/day, so total work = 12 units. In 4 days, they complete 4 units. Remaining work = 12 - 4 = 8 units. B completes 8 units in 14 days, so B's efficiency = 8 / 14 = 4/7 units/day. Efficiency of A = 1 - 4/7 = 3/7 units/day. Time taken by A alone = 12 / (3/7) = (12 * 7) / 3 = 28 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 13 days and B in 20 days. If they work together, the work will be completed in:
A. 22.88
B. 17.88
C. 7.88
D. 12.88

Correct Answer: Option C


Explanation:
Combined rate = 1/13 + 1/20. Required time = 7.88 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 12 days and B can complete the same work in 22 days. If they work together, in how many days will the work be completed?
A. 13.76
B. 9.76
C. 7.76
D. 11.76

Correct Answer: Option C


Explanation:
Combined rate = 1/12 + 1/22. Time = 1 ÷ combined rate = 7.76 days.

This question belongs to: Maths Time and Work
Question #3
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A. 12 days
B. 10 days
C. 8 days
D. 6 days

Correct Answer: Option B


Explanation:
Total work = LCM(20, 12) = 60 units. Efficiency of A = 3, B = 5. In 4 days, A alone completes = 4 * 3 = 12 units. Remaining work = 60 - 12 = 48 units. Combined efficiency of A and B = 3 + 5 = 8. Time taken together for remaining work = 48 / 8 = 6 days. Total duration of work = 4 + 6 = 10 days.

This question belongs to: Maths Time and Work