A can complete a work in 23 days. What percentage of the work will be completed in 7 days? MCQ with Answer and Explanation

A can complete a work in 23 days. What percentage of the work will be completed in 7 days?
A. 37.93
B. 32.93
C. 35.43
D. 30.43
Answer: Option D
Solution (By JKSSB Mock Tests)
Completed percentage = (7/23)×100 = 30.43%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
A. 10.5 days
B. 6 days
C. 5 days
D. 10 days

Correct Answer: Option D


Explanation:
Total work = LCM(24, 9, 12) = 72 units. Efficiency of A = 3, B = 8, C = 6. B and C work for 3 days: work done = 3 * (8 + 6) = 3 * 14 = 42 units. Remaining work = 72 - 42 = 30 units. Time taken by A to complete remaining work = 30 / 3 = 10 days.

This question belongs to: Maths Time and Work
Question #2
17 men can complete a work in 21 days. If 21 men work at the same rate, in how many days will the work be completed?
A. 23.0
B. 17.0
C. 19.0
D. 21.0

Correct Answer: Option B


Explanation:
Total work = 17 × 21 = 357 man-days. Required days = 357/21 = 17.0 days.

This question belongs to: Maths Time and Work
Question #3
A can do a work in 9 days and B in 29 days. In how many days will they complete 75% of the work together?
A. 5.15
B. 10.15
C. 12.65
D. 7.65

Correct Answer: Option A


Explanation:
Combined time for full work multiplied by 0.75 = 5.15 days.

This question belongs to: Maths Time and Work