A can do a work in 9 days and B in 29 days. In how many days will they complete 75% of the work together? MCQ with Answer and Explanation

A can do a work in 9 days and B in 29 days. In how many days will they complete 75% of the work together?
A. 12.65
B. 5.15
C. 7.65
D. 10.15
Answer: Option B
Solution (By JKSSB Mock Tests)
Combined time for full work multiplied by 0.75 = 5.15 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 14 days and B in 12 days. If they work together, the work will be completed in:
A. 21.46
B. 6.46
C. 11.46
D. 16.46

Correct Answer: Option B


Explanation:
Combined rate = 1/14 + 1/12. Required time = 6.46 days.

This question belongs to: Maths Time and Work
Question #2
17 men can complete a work in 15 days. If 21 men work at the same rate, in how many days will the work be completed?
A. 14.14
B. 16.14
C. 18.14
D. 12.14

Correct Answer: Option D


Explanation:
Total work = 17 × 15 = 255 man-days. Required days = 255/21 = 12.14 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 15 days and B can complete the same work in 25 days. If they work together, in how many days will the work be completed?
A. 9.38
B. 15.38
C. 11.38
D. 13.38

Correct Answer: Option A


Explanation:
Combined rate = 1/15 + 1/25. Time = 1 ÷ combined rate = 9.38 days.