A is 40% more efficient than B. If B alone can complete a work in 14 days, then in how many days can A alone complete the same work? MCQ with Answer and Explanation

A is 40% more efficient than B. If B alone can complete a work in 14 days, then in how many days can A alone complete the same work?
A. 8 days
B. 12 days
C. 9 days
D. 10 days
Answer: Option D
Solution (By JKSSB Mock Tests)
Let efficiency of B = 100, then efficiency of A = 140. Ratio of efficiency of A : B = 140 : 100 = 7 : 5. Total work = Efficiency of B * Time of B = 5 * 14 = 70 units. Time taken by A alone = 70 / 7 = 10 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B can do a piece of work in 10 days and 15 days respectively. They work together for 2 days and then A is replaced by C. The work is finished in next 4 days. In how many days can C alone finish the work?
A. 10 days
B. 15 days
C. 12 days
D. 8 days

Correct Answer: Option A


Explanation:
Total work = LCM(10, 15) = 30 units. Efficiency of A = 3, B = 2. In 2 days, A and B do 2 * (3 + 2) = 10 units. Remaining work = 30 - 10 = 20 units. This is completed by B and C in 4 days, so combined efficiency of B and C = 20 / 4 = 5 units/day. Since efficiency of B = 2, efficiency of C = 5 - 2 = 3 units/day. Time taken by C alone = 30 / 3 = 10 days.

This question belongs to: Maths Time and Work
Question #2
A and B together can do a piece of work in 8 days, B and C together in 12 days, and C and A together in 16 days. In how many days can A, B and C together finish the work?
A. 8(2/13) days
B. 6(6/13) days
C. 5(5/13) days
D. 7(5/13) days

Correct Answer: Option D


Explanation:
Total work = LCM(8, 12, 16) = 48 units. Efficiency of (A+B) = 6, (B+C) = 4, (C+A) = 3. Summing efficiencies gives 2 * (A+B+C) = 13, so efficiency of (A+B+C) = 13/2. Time taken = 48 / (13/2) = 96 / 13 = 7(5/13) days.

This question belongs to: Maths Time and Work
Question #3
A can do a work in 17 days and B in 29 days. In how many days will they complete 75% of the work together?
A. 15.54
B. 10.54
C. 8.04
D. 13.04

Correct Answer: Option C


Explanation:
Combined time for full work multiplied by 0.75 = 8.04 days.