A and B can do a piece of work in 10 days and 15 days respectively. They work together for 2 days and then A is replaced by C. The work is finished in next 4 days. In how many days can C alone finish the work? MCQ with Answer and Explanation

A and B can do a piece of work in 10 days and 15 days respectively. They work together for 2 days and then A is replaced by C. The work is finished in next 4 days. In how many days can C alone finish the work?
A. 8 days
B. 10 days
C. 15 days
D. 12 days
Answer: Option B
Solution (By JKSSB Mock Tests)
Total work = LCM(10, 15) = 30 units. Efficiency of A = 3, B = 2. In 2 days, A and B do 2 * (3 + 2) = 10 units. Remaining work = 30 - 10 = 20 units. This is completed by B and C in 4 days, so combined efficiency of B and C = 20 / 4 = 5 units/day. Since efficiency of B = 2, efficiency of C = 5 - 2 = 3 units/day. Time taken by C alone = 30 / 3 = 10 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can finish a work in 10 days and B in 15 days. B starts the work and is joined by A after 5 days. What is the total number of days taken to complete the work?
A. 7 days
B. 6 days
C. 8 days
D. 9 days

Correct Answer: Option D


Explanation:
Total work = LCM(10, 15) = 30 units. Efficiency of A = 3, B = 2. B works alone for 5 days: work completed = 5 * 2 = 10 units. Remaining work = 30 - 10 = 20 units. Now A and B work together with efficiency = 3 + 2 = 5 units/day. Time taken for remaining work = 20 / 5 = 4 days. Total time = 5 + 4 = 9 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 16 days and B in 29 days. If they work together, the work will be completed in:
A. 20.31
B. 15.31
C. 25.31
D. 10.31

Correct Answer: Option D


Explanation:
Combined rate = 1/16 + 1/29. Required time = 10.31 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 19 days and B in 38 days. After working together for 5 days, what percentage of work remains?
A. 63.03
B. 68.03
C. 60.53
D. 65.53

Correct Answer: Option C


Explanation:
Remaining work = (1 - 5*(1/19+1/38))×100 = 60.53%.

This question belongs to: Maths Time and Work