A can finish a work in 10 days and B in 15 days. B starts the work and is joined by A after 5 days. What is the total number of days taken to complete the work? MCQ with Answer and Explanation

A can finish a work in 10 days and B in 15 days. B starts the work and is joined by A after 5 days. What is the total number of days taken to complete the work?
A. 9 days
B. 6 days
C. 7 days
D. 8 days
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = LCM(10, 15) = 30 units. Efficiency of A = 3, B = 2. B works alone for 5 days: work completed = 5 * 2 = 10 units. Remaining work = 30 - 10 = 20 units. Now A and B work together with efficiency = 3 + 2 = 5 units/day. Time taken for remaining work = 20 / 5 = 4 days. Total time = 5 + 4 = 9 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
A. 20 days
B. 35 days
C. 30 days
D. 25 days

Correct Answer: Option D


Explanation:
Total work = LCM(10, 50) = 50 units. Efficiency of (A + B) = 5, efficiency of C = 1. Total efficiency of (A + B + C) = 5 + 1 = 6. Given A = B + C. So, (B + C) + B + C = 6 => 2(B + C) = 6 => B + C = 3. Since C = 1, B = 2. Time taken by B alone = 50 / 2 = 25 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 30 days. What percentage of work will A complete in 6 days?
A. 30.0
B. 20.0
C. 25.0
D. 35.0

Correct Answer: Option B


Explanation:
Percentage completed = (6/30) × 100 = 20.0%.

This question belongs to: Maths Time and Work
Question #3
8 men can complete a work in 24 days. If 12 men work at the same rate, in how many days will the work be completed?
A. 22.0
B. 20.0
C. 16.0
D. 18.0

Correct Answer: Option C


Explanation:
Total work = 8 × 24 = 192 man-days. Required days = 192/12 = 16.0 days.

This question belongs to: Maths Time and Work