A can complete a work in 30 days. What percentage of work will A complete in 6 days? MCQ with Answer and Explanation

A can complete a work in 30 days. What percentage of work will A complete in 6 days?
A. 25.0
B. 30.0
C. 20.0
D. 35.0
Answer: Option C
Solution (By JKSSB Mock Tests)
Percentage completed = (6/30) × 100 = 20.0%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can do a work in 17 days and B in 17 days. In how many days will they complete 75% of the work together?
A. 13.88
B. 8.88
C. 6.38
D. 11.38

Correct Answer: Option C


Explanation:
Combined time for full work multiplied by 0.75 = 6.38 days.

This question belongs to: Maths Time and Work
Question #2
A, B and C can do a piece of work in 20, 30 and 60 days respectively. If A works everyday and is assisted by B and C together on every third day, then in how many days will the work be completed?
A. 20 days
B. 15 days
C. 18 days
D. 12 days

Correct Answer: Option B


Explanation:
Total work = LCM(20, 30, 60) = 60 units. Efficiency of A = 3, B = 2, C = 1. Day 1: A works = 3 units. Day 2: A works = 3 units. Day 3: A+B+C work = 3 + 2 + 1 = 6 units. Work done in 3 days = 3 + 3 + 6 = 12 units. Number of 3-day cycles to complete 60 units = 60 / 12 = 5 cycles. Total days = 5 * 3 = 15 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 21 days and B can complete the same work in 31 days. If they work together, in how many days will the work be completed?
A. 16.52
B. 12.52
C. 18.52
D. 14.52

Correct Answer: Option B


Explanation:
Combined rate = 1/21 + 1/31. Time = 1 ÷ combined rate = 12.52 days.

This question belongs to: Maths Time and Work