A can do a work in 17 days and B in 17 days. In how many days will they complete 75% of the work together? MCQ with Answer and Explanation

A can do a work in 17 days and B in 17 days. In how many days will they complete 75% of the work together?
A. 6.38
B. 8.88
C. 11.38
D. 13.88
Answer: Option A
Solution (By JKSSB Mock Tests)
Combined time for full work multiplied by 0.75 = 6.38 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 10 days and B in 30 days. If they work together, the work will be completed in:
A. 12.5
B. 7.5
C. 22.5
D. 17.5

Correct Answer: Option B


Explanation:
Combined rate = 1/10 + 1/30. Required time = 7.5 days.

This question belongs to: Maths Time and Work
Question #2
10 men can complete a work in 7 days. But 10 women can complete the same work in 14 days. If 5 men and 10 women work together, in how many days will the work be completed?
A. 8 days
B. 6 days
C. 7 days
D. 5 days

Correct Answer: Option C


Explanation:
Efficiency of 10 men = 1/7, so 1 man = 1/70. Efficiency of 10 women = 1/14. Efficiency of 5 men and 10 women = 5*(1/70) + 1/14 = 1/14 + 1/14 = 2/14 = 1/7. Thus, they will complete the work in 7 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 18 days. What percentage of work will A complete in 6 days?
A. 33.33
B. 43.33
C. 48.33
D. 38.33

Correct Answer: Option A


Explanation:
Percentage completed = (6/18) × 100 = 33.33%.

This question belongs to: Maths Time and Work