A, B and C can do a piece of work in 20, 30 and 60 days respectively. If A works everyday and is assisted by B and C together on every third day, then in how many days will the work be completed? MCQ with Answer and Explanation

A, B and C can do a piece of work in 20, 30 and 60 days respectively. If A works everyday and is assisted by B and C together on every third day, then in how many days will the work be completed?
A. 15 days
B. 12 days
C. 20 days
D. 18 days
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = LCM(20, 30, 60) = 60 units. Efficiency of A = 3, B = 2, C = 1. Day 1: A works = 3 units. Day 2: A works = 3 units. Day 3: A+B+C work = 3 + 2 + 1 = 6 units. Work done in 3 days = 3 + 3 + 6 = 12 units. Number of 3-day cycles to complete 60 units = 60 / 12 = 5 cycles. Total days = 5 * 3 = 15 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B can complete a piece of work in 18 days and 24 days respectively. They worked together for 6 days and then A left. In how many days will B complete the remaining work?
A. 10 days
B. 12 days
C. 8 days
D. 14 days

Correct Answer: Option A


Explanation:
Total work = LCM(18, 24) = 72 units. Efficiency of A = 4, B = 3. Combined efficiency = 7. In 6 days, work done = 6 * 7 = 42 units. Remaining work = 72 - 42 = 30 units. Time taken by B to finish remaining work = 30 / 3 = 10 days.

This question belongs to: Maths Time and Work
Question #2
A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can A alone complete the work?
A. 20 days
B. 30 days
C. 40 days
D. 24 days

Correct Answer: Option B


Explanation:
Total work = LCM(12, 15, 20) = 60 units. Efficiency of (A+B) = 5, (B+C) = 4, (C+A) = 3. Summing these gives 2*(A+B+C) = 12 => Efficiency of (A+B+C) = 6. Efficiency of A = (A+B+C) - (B+C) = 6 - 4 = 2. Time taken by A alone = 60 / 2 = 30 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 10 days and B in 27 days. If they work together, the work will be completed in:
A. 7.3
B. 22.3
C. 17.3
D. 12.3

Correct Answer: Option A


Explanation:
Combined rate = 1/10 + 1/27. Required time = 7.3 days.