If 12 men and 16 boys can do a piece of work in 5 days; while 13 men and 24 boys can do it in 4 days, then the ratio of the daily work done by a man to that of a boy is: MCQ with Answer and Explanation

If 12 men and 16 boys can do a piece of work in 5 days; while 13 men and 24 boys can do it in 4 days, then the ratio of the daily work done by a man to that of a boy is:
A. 3 : 1
B. 2 : 1
C. 3 : 2
D. 5 : 4
Answer: Option B
Solution (By JKSSB Mock Tests)
Total work = 5 * (12M + 16B) = 4 * (13M + 24B) => 60M + 80B = 52M + 96B => 8M = 16B => M/B = 16/8 = 2/1. Thus, the ratio is 2 : 1.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can finish a work in 15 days and B in 25 days. They start together but B leaves 5 days before the completion of the work. Find the total number of days taken to complete the work.
A. 12.5 days
B. 11.25 days
C. 10 days
D. 13.25 days

Correct Answer: Option B


Explanation:
Total work = LCM(15, 25) = 75 units. Efficiency of A = 5, B = 3. Let total days be x. A works for x days, B works for (x - 5) days. 5x + 3(x - 5) = 75 => 8x - 15 = 75 => 8x = 90 => x = 90/8 = 11.25 days.

This question belongs to: Maths Time and Work
Question #2
Two pipes A and B can fill a cistern in 12 minutes and 15 minutes respectively. There is also a waste pipe C. If all three pipes are opened together, the cistern is full in 20 minutes. How long will C take to empty the full cistern?
A. 15 minutes
B. 12 minutes
C. 8 minutes
D. 10 minutes

Correct Answer: Option D


Explanation:
Total capacity = LCM(12, 15, 20) = 60 units. Efficiency of A = 5, B = 4. Combined efficiency of A+B+C = 3. Efficiency of C = 3 - (5 + 4) = -6. Thus, C empties 6 units/minute. Time taken by C to empty the full cistern = 60 / 6 = 10 minutes.

This question belongs to: Maths Time and Work
Question #3
23 men can complete a work in 30 days. If 28 men work at the same rate, the work will be completed in:
A. 34.64
B. 24.64
C. 29.64
D. 39.64

Correct Answer: Option B


Explanation:
Total work = 690 man-days. Time = 690/28 = 24.64 days.

This question belongs to: Maths Time and Work