A can finish a work in 15 days and B in 25 days. They start together but B leaves 5 days before the completion of the work. Find the total number of days taken to complete the work. MCQ with Answer and Explanation

A can finish a work in 15 days and B in 25 days. They start together but B leaves 5 days before the completion of the work. Find the total number of days taken to complete the work.
A. 12.5 days
B. 10 days
C. 13.25 days
D. 11.25 days
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = LCM(15, 25) = 75 units. Efficiency of A = 5, B = 3. Let total days be x. A works for x days, B works for (x - 5) days. 5x + 3(x - 5) = 75 => 8x - 15 = 75 => 8x = 90 => x = 90/8 = 11.25 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 20 days and B in 36 days. If both work together, in how many days will the work be completed?
A. 20.36
B. 12.86
C. 15.36
D. 17.86

Correct Answer: Option B


Explanation:
Combined rate = 1/20 + 1/36. Time = 12.86 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 24 days and B in 45 days. If both work together, in how many days will the work be completed?
A. 20.65
B. 15.65
C. 18.15
D. 23.15

Correct Answer: Option B


Explanation:
Combined rate = 1/24 + 1/45. Time = 15.65 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 9 days and B in 13 days. If they work together, the work will be completed in:
A. 10.32
B. 5.32
C. 15.32
D. 20.32

Correct Answer: Option B


Explanation:
Combined rate = 1/9 + 1/13. Required time = 5.32 days.