Solution (By JKSSB Mock Tests)
Total work = LCM(12, 16) = 48 units. Efficiency of A = 4, B = 3. Combined efficiency = 7 units/day. In 3 days, work completed = 3 * 7 = 21 units. Remaining work = 48 - 21 = 27 units. Time taken by B to complete remaining work = 27 / 3 = 9 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
12 men can complete a work in 14 days. If 17 men work at the same rate, the work will be completed in:
A. 19.88
B. 14.88
C. 24.88
D. 9.88

Correct Answer: Option D


Explanation:
Total work = 168 man-days. Time = 168/17 = 9.88 days.

This question belongs to: Maths Time and Work
Question #2
A can do a work in 24 days and B in 32 days. If they work together and get Rs. 5600 for the work, what is B's share?
A. Rs. 2400
B. Rs. 2800
C. Rs. 3200
D. Rs. 3000

Correct Answer: Option A


Explanation:
Ratio of time taken by A : B = 24 : 32 = 3 : 4. Ratio of efficiency of A : B = 4 : 3. Total ratio parts = 4 + 3 = 7. B's share = (3 / 7) * 5600 = 3 * 800 = Rs. 2400.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 23 days and B can complete the same work in 18 days. If they work together, in how many days will the work be completed?
A. 14.1
B. 10.1
C. 12.1
D. 16.1

Correct Answer: Option B


Explanation:
Combined rate = 1/23 + 1/18. Time = 1 ÷ combined rate = 10.1 days.