A and B can complete a work in 12 days and 16 days respectively. Both work together for 3 days and then A leaves. How long will B take to complete the remaining work? MCQ with Answer and Explanation
A and B can complete a work in 12 days and 16 days respectively. Both work together for 3 days and then A leaves. How long will B take to complete the remaining work?
A. 10 days
B. 11 days
C. 9 days
D. 8 days
Answer: Option C
Solution (By JKSSB Mock Tests)
Total work = LCM(12, 16) = 48 units. Efficiency of A = 4, B = 3. Combined efficiency = 7 units/day. In 3 days, work completed = 3 * 7 = 21 units. Remaining work = 48 - 21 = 27 units. Time taken by B to complete remaining work = 27 / 3 = 9 days.
Explanation:
Ratio of time taken by A : B = 24 : 32 = 3 : 4. Ratio of efficiency of A : B = 4 : 3. Total ratio parts = 4 + 3 = 7. B's share = (3 / 7) * 5600 = 3 * 800 = Rs. 2400.