A and B together can do a piece of work in 6 days. If A alone can do it in 18 days, in how many days can B alone complete the work? MCQ with Answer and Explanation

A and B together can do a piece of work in 6 days. If A alone can do it in 18 days, in how many days can B alone complete the work?
A. 20 days
B. 9 days
C. 12 days
D. 15 days
Answer: Option B
Solution (By JKSSB Mock Tests)
Combined 1-day work = 1/6. A's 1-day work = 1/18. B's 1-day work = 1/6 - 1/18 = 2/18 = 1/9. Therefore, B alone can complete the work in 9 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
13 men can complete a work in 29 days. If 17 men work at the same rate, in how many days will the work be completed?
A. 28.18
B. 24.18
C. 22.18
D. 26.18

Correct Answer: Option C


Explanation:
Total work = 13 × 29 = 377 man-days. Required days = 377/17 = 22.18 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 22 days and B in 12 days. If they work together, the work will be completed in:
A. 22.76
B. 17.76
C. 7.76
D. 12.76

Correct Answer: Option C


Explanation:
Combined rate = 1/22 + 1/12. Required time = 7.76 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 24 days and B in 23 days. If both work together, in how many days will the work be completed?
A. 19.24
B. 11.74
C. 14.24
D. 16.74

Correct Answer: Option B


Explanation:
Combined rate = 1/24 + 1/23. Time = 11.74 days.

This question belongs to: Maths Time and Work