A and B work together. A alone can complete the work in 24 days and B alone in 24 days. What percentage of the total daily work is contributed by A? MCQ with Answer and Explanation

A and B work together. A alone can complete the work in 24 days and B alone in 24 days. What percentage of the total daily work is contributed by A?
A. 55.0
B. 50.0
C. 52.5
D. 57.5
Answer: Option B
Solution (By JKSSB Mock Tests)
A share = (1/24) / (1/24+1/24) ×100 = 50.0%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 13 days and B can complete the same work in 33 days. If they work together, in how many days will the work be completed?
A. 9.33
B. 11.33
C. 13.33
D. 15.33

Correct Answer: Option A


Explanation:
Combined rate = 1/13 + 1/33. Time = 1 ÷ combined rate = 9.33 days.

This question belongs to: Maths Time and Work
Question #2
A and B can complete a work together in 15 days. They work together for 3 days, then A leaves. If B alone completes the remaining work in 16 days, in how many days can A alone complete the whole work?
A. 45 days
B. 60 days
C. 75 days
D. 30 days

Correct Answer: Option B


Explanation:
Let the total work be 60 units. Combined efficiency of A and B = 60 / 15 = 4 units/day. In 3 days, they complete 3 * 4 = 12 units. Remaining work = 60 - 12 = 48 units. B completes 48 units in 16 days, so B's efficiency = 48 / 16 = 3 units/day. A's efficiency = 4 - 3 = 1 unit/day. Time taken by A alone = 60 / 1 = 60 days.

This question belongs to: Maths Time and Work
Question #3
A can do a piece of work in 14 days and B in 21 days. They begin together but 3 days before the completion of the work, A leaves. The total number of days taken to complete the work is:
A. 9(1/5) days
B. 10(1/5) days
C. 8(3/5) days
D. 7(2/5) days

Correct Answer: Option B


Explanation:
Total work = LCM(14, 21) = 42 units. Efficiency of A = 3, B = 2. Let total days be x. A works for (x - 3) days and B works for x days. 3*(x - 3) + 2*x = 42 => 3x - 9 + 2x = 42 => 5x = 51 => x = 51/5 = 10(1/5) days.

This question belongs to: Maths Time and Work