A, B and C can do a piece of work in 10, 15 and 30 days respectively. If they work on alternate days in the order A, B, C, in how many days will the work be completed? MCQ with Answer and Explanation

A, B and C can do a piece of work in 10, 15 and 30 days respectively. If they work on alternate days in the order A, B, C, in how many days will the work be completed?
A. 12 days
B. 18 days
C. 15 days
D. 20 days
Answer: Option C
Solution (By JKSSB Mock Tests)
Total work = LCM(10, 15, 30) = 30 units. Efficiency of A = 3, B = 2, C = 1. In a 3-day cycle (A on day 1, B on day 2, C on day 3), work completed = 3 + 2 + 1 = 6 units. Number of cycles required = 30 / 6 = 5 cycles. Total days = 5 * 3 = 15 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can do a piece of work in 10 days, B in 12 days and C in 15 days. They carry out the work together and get a total of Rs. 4500 as wages. Find the share of C.
A. Rs. 1000
B. Rs. 1800
C. Rs. 1500
D. Rs. 1200

Correct Answer: Option D


Explanation:
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Ratio of wages = 6 : 5 : 4. Total ratio parts = 15. Share of C = (4 / 15) * 4500 = 4 * 300 = Rs. 1200.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 15 days and B can complete the same work in 25 days. If they work together, in how many days will the work be completed?
A. 15.38
B. 9.38
C. 11.38
D. 13.38

Correct Answer: Option B


Explanation:
Combined rate = 1/15 + 1/25. Time = 1 ÷ combined rate = 9.38 days.

This question belongs to: Maths Time and Work
Question #3
15 men can complete a work in 25 days. If 19 men work at the same rate, in how many days will the work be completed?
A. 25.74
B. 21.74
C. 23.74
D. 19.74

Correct Answer: Option D


Explanation:
Total work = 15 × 25 = 375 man-days. Required days = 375/19 = 19.74 days.

This question belongs to: Maths Time and Work