A can complete a work in 11 days and B can complete the same work in 31 days. If they work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 11 days and B can complete the same work in 31 days. If they work together, in how many days will the work be completed?
A. 12.12
B. 8.12
C. 10.12
D. 14.12
Answer: Option B
Solution (By JKSSB Mock Tests)
Combined rate = 1/11 + 1/31. Time = 1 ÷ combined rate = 8.12 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can do a work in 15 days and B in 17 days. In how many days will they complete 75% of the work together?
A. 10.98
B. 5.98
C. 8.48
D. 13.48

Correct Answer: Option B


Explanation:
Combined time for full work multiplied by 0.75 = 5.98 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 22 days and B can complete the same work in 17 days. If they work together, in how many days will the work be completed?
A. 15.59
B. 9.59
C. 11.59
D. 13.59

Correct Answer: Option B


Explanation:
Combined rate = 1/22 + 1/17. Time = 1 ÷ combined rate = 9.59 days.

This question belongs to: Maths Time and Work
Question #3
19 men can complete a work in 17 days. If 23 men work at the same rate, in how many days will the work be completed?
A. 14.04
B. 20.04
C. 16.04
D. 18.04

Correct Answer: Option A


Explanation:
Total work = 19 × 17 = 323 man-days. Required days = 323/23 = 14.04 days.

This question belongs to: Maths Time and Work