A can complete a work in 12 days and B can complete the same work in 32 days. If they work together, in how many days will the work be completed? MCQ with Answer and Explanation
Explanation:
Let efficiency of B = 2, then efficiency of A = 3. Total work = Efficiency of A * Time of A = 3 * 12 = 36 units. Time taken by B = 36 / 2 = 18 days.