A can complete a work in 12 days and B in 17 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 12 days and B in 17 days. If they work together, the work will be completed in:
A. 17.03
B. 22.03
C. 12.03
D. 7.03
Answer: Option D
Solution (By JKSSB Mock Tests)
Combined rate = 1/12 + 1/17. Required time = 7.03 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B together can complete a piece of work in 8 days. If A alone can complete the same work in 12 days, in how many days can B alone complete it?
A. 20 days
B. 18 days
C. 16 days
D. 24 days

Correct Answer: Option D


Explanation:
Total work = LCM(8, 12) = 24 units. Combined efficiency of A and B = 3. Efficiency of A = 2. Efficiency of B = 3 - 2 = 1. Time taken by B alone = 24 / 1 = 24 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 23 days and B in 28 days. If both work together, in how many days will the work be completed?
A. 20.13
B. 15.13
C. 12.63
D. 17.63

Correct Answer: Option C


Explanation:
Combined rate = 1/23 + 1/28. Time = 12.63 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 16 days and B in 20 days. If both work together, in how many days will the work be completed?
A. 16.39
B. 13.89
C. 8.89
D. 11.39

Correct Answer: Option C


Explanation:
Combined rate = 1/16 + 1/20. Time = 8.89 days.

This question belongs to: Maths Time and Work