A can complete a work in 13 days and B in 17 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 13 days and B in 17 days. If they work together, the work will be completed in:
A. 12.37
B. 17.37
C. 7.37
D. 22.37
Answer: Option C
Solution (By JKSSB Mock Tests)
Combined rate = 1/13 + 1/17. Required time = 7.37 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 22 days and B in 12 days. If they work together, the work will be completed in:
A. 22.76
B. 7.76
C. 17.76
D. 12.76

Correct Answer: Option B


Explanation:
Combined rate = 1/22 + 1/12. Required time = 7.76 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 18 days and B can complete the same work in 28 days. If they work together, in how many days will the work be completed?
A. 12.96
B. 14.96
C. 16.96
D. 10.96

Correct Answer: Option D


Explanation:
Combined rate = 1/18 + 1/28. Time = 1 ÷ combined rate = 10.96 days.

This question belongs to: Maths Time and Work
Question #3
A and B can complete a piece of work in 12 and 18 days respectively. They begin the work together, but A leaves 4 days before the completion of the work. For how many days did A and B work together?
A. 5 days
B. 5.6 days
C. 4.4 days
D. 6 days

Correct Answer: Option B


Explanation:
Total work = LCM(12, 18) = 36 units. Efficiency of A = 3, B = 2. Let total days be x. B works for x days, A works for (x - 4) days. 3(x - 4) + 2x = 36 => 3x - 12 + 2x = 36 => 5x = 48 => x = 9.6 days. A and B worked together for x - 4 = 9.6 - 4 = 5.6 days.