A can complete a work in 16 days and B can complete the same work in 16 days. If they work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 16 days and B can complete the same work in 16 days. If they work together, in how many days will the work be completed?
A. 14.0
B. 8.0
C. 10.0
D. 12.0
Answer: Option B
Solution (By JKSSB Mock Tests)
Combined rate = 1/16 + 1/16. Time = 1 ÷ combined rate = 8.0 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 16 days and B in 21 days. If they work together, the work will be completed in:
A. 19.08
B. 9.08
C. 24.08
D. 14.08

Correct Answer: Option B


Explanation:
Combined rate = 1/16 + 1/21. Required time = 9.08 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 14 days and B in 23 days. If they work together, the work will be completed in:
A. 13.7
B. 23.7
C. 18.7
D. 8.7

Correct Answer: Option D


Explanation:
Combined rate = 1/14 + 1/23. Required time = 8.7 days.

This question belongs to: Maths Time and Work
Question #3
If 8 men and 12 boys can finish a piece of work in 10 days, while 6 men and 8 boys can finish it in 14 days, find the time taken by 1 man alone to complete the work.
A. 120 days
B. 100 days
C. 160 days
D. 140 days

Correct Answer: Option D


Explanation:
Total work = 10 * (8M + 12B) = 14 * (6M + 8B) => 80M + 120B = 84M + 112B => 4M = 8B => 1M = 2B. Total work = 10 * (8M + 6M) = 140M. Thus, 1 man alone will take 140 days.

This question belongs to: Maths Time and Work