A can complete a work in 17 days and B can complete the same work in 27 days. If they work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 17 days and B can complete the same work in 27 days. If they work together, in how many days will the work be completed?
A. 10.43
B. 16.43
C. 12.43
D. 14.43
Answer: Option A
Solution (By JKSSB Mock Tests)
Combined rate = 1/17 + 1/27. Time = 1 ÷ combined rate = 10.43 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can build a wall in 30 days, while B can destroy it in 40 days. If they work on alternate days starting with A, in how many days will the wall be built?
A. 237 days
B. 240 days
C. 233 days
D. 235 days

Correct Answer: Option C


Explanation:
Total work = LCM(30, 40) = 120 units. Efficiency of A = +4, B = -3. In 2 days, net work = 4 - 3 = 1 unit. We look for when the work reaches 120 - 4 = 116 units. 116 units are done in 116 * 2 = 232 days. On the 233rd day, A works and completes 4 units, making total work 116 + 4 = 120 units. Thus, the wall is completed in 233 days.

This question belongs to: Maths Time and Work
Question #2
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A. 8 days
B. 6 days
C. 10 days
D. 12 days

Correct Answer: Option C


Explanation:
Total work = LCM(20, 12) = 60 units. Efficiency of A = 3, B = 5. In 4 days, A alone completes = 4 * 3 = 12 units. Remaining work = 60 - 12 = 48 units. Combined efficiency of A and B = 3 + 5 = 8. Time taken together for remaining work = 48 / 8 = 6 days. Total duration of work = 4 + 6 = 10 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 13 days and B can complete the same work in 28 days. If they work together, in how many days will the work be completed?
A. 8.88
B. 12.88
C. 14.88
D. 10.88

Correct Answer: Option A


Explanation:
Combined rate = 1/13 + 1/28. Time = 1 ÷ combined rate = 8.88 days.

This question belongs to: Maths Time and Work